I have a cluster with where each node can run up to 8 map tasks (one task
per core), now we realized that we need to run another type of job that has
much larger memory requirements, which will only allow up to 4 tasks to be
run on each node. Is it possible to somehow specify that each map process of
that new task "occupies" two map slots so that at most 4 such maps will be
launched?



Another option is of course to change map.tasks.maximum to 4 and rewrite
all old tasks to run couple of threads, but if there's better solution I'd
highly appreciate any advice!

Search Discussions

Discussion Posts

Follow ups

Related Discussions

Discussion Navigation
viewthread | post
posts ‹ prev | 1 of 3 | next ›
Discussion Overview
groupcommon-user @
categorieshadoop
postedApr 10, '10 at 11:03p
activeApr 11, '10 at 1:54a
posts3
users2
websitehadoop.apache.org...
irc#hadoop

2 users in discussion

Dmitry Pushkarev: 2 posts Arun C Murthy: 1 post

People

Translate

site design / logo © 2022 Grokbase